All projects36%50%In ProgressIn ProgressIn ProgressIn ProgressIn Progress
ConstructionNBV-04
Noir Bayview
Banani, DhakaSumaiya K.Launch Aug 2024Handover Mar 2027
Total Units
56
31 sold
Sold
8.2%31
55% sell-through
Available
25
On market
Revenue
12.4%৳ 98.00 Cr
To date
Construction
42%
Construction
Revenue vs Expense
Last 6 months
Project owner
SK
Sumaiya K.
Project Lead · Reverie Holdings
Launch
Aug 20, 2024
Handover
Mar 15, 2027
P&L Snapshot
Revenue to date৳ 98.00 Cr
Expense to date৳ 61.00 Cr
Gross margin37.8%
Buildings
2 towers
Tower A7 floors · 28 units
Tower B7 floors · 28 units
Upcoming Milestones
Foundation & piling
Phase 2 · 62% complete
Substructure RCC
Phase 2 · 52% complete
Superstructure framing
Phase 3 · 42% complete
MEP rough-in
Phase 3 · 28% complete
Facade & glazing
Phase 4 · 14% complete
Recent Transactions
| 2025-01-14 | Inflow | Booking | Unit booking — buyer Mehedi | ৳ 94.07 L |
| 2025-02-25 | Inflow | Installment | Installment settlement #1001 | ৳ 2.54 Cr |
| 2025-03-22 | Outflow | Materials | Materials settlement #1002 | ৳ 1.73 Cr |
| 2025-04-15 | Outflow | Labor wages | Labor wages settlement #1003 | ৳ 2.52 Cr |
| 2025-05-22 | Outflow | Contractor | Contractor settlement #1004 | ৳ 1.33 Cr |
| 2025-06-13 | Outflow | Marketing | Marketing settlement #1005 | ৳ 1.43 Cr |